Construction of Sea Water Reverse Osmosis Satellite desalination plants
Construction of Sea Water Reverse Osmosis Satellite desalination plants
Location:
West Coast, Saudi Arabia
Client:
Saline Water Conversion Corporation (SWCC)
Supervision Consultant:
TRACTEBEL
Contract Type:
Lump Sum
Contract Duration:
15 Months
Defects liability period:
24 Months
Contract Signature:
21st February 2019
Project Commencement:
13th January 2019 (site handover)
Water Production Date:
13th April 2020
The EPC Contract will be executed by consortium identified as ASRF Consortium and constituted between the following companies:
- Advance Water Technology (AWT), Riyadh, Saudi Arabia
- SETE Energy Saudia , Jeddah, Saudi Arabia
- RAWAFID, Jeddah, Saudi Arabia
AL-FATAH, Jeddah, Saudi Arabia






Works